X can do a piece of work in 20 days, while Y can do in 10 days. If Y worked at it for 8 days,then X can finish the remaining work in______.?

A)
2 days

B)
3 days

C)
4 days

D)
5 days


Correct Answer :

4 days


Explanation :

Y's 8 day's work = 8*(1/10) = 4/5
Remaining work = (1 - 4/5) = 1/5
1/5 work is done by X = 20*(1/5) = 4 days

Post comment
Cancel
Thanks for your comment.!
Write a comment(Click here) ...
View in English View in Hindi

A is twice as good as workman as B and therefore able to finish a piece of work in 30 days less than B. In how many days can they complete the whole work together?

A)
20 days

B)
40 days

C)
60 days

D)
80 days


Correct Answer :

20 days


Explanation :

Let A takes X days to complete the work and B takes 2X days
according to question, A takes 30 days less than B, that is X = 2X – 30
X=30

thus ,A take 30 days to complete the work and B takes 60 days
hence, A and B one days work is 1/30 + 1/60 = 1/20

Therefore, the whole job together they will be completed in 20 days

16 workers working 6 hours day can build a wall of length 150m, breadth 20m, and height 12m in 25 days. In how many days 12 workers, working 8 hours a day will build a wall of length 800m, breadth 15m and height 6m?

A)
50 days

B)
25 days

C)
25 days

D)
60 days


Correct Answer :

50 days


Explanation :

to build a wall of 150*20*12=36000 ,hours required = 16*6*25=2400

to build a wall of 800*15*6=72000 , which is exactly twice as big as the first one,
You need 2400*2 hours = 4800
that is 12*8*days = 4800
days = 4800/96 = 50

A can do a piece of work in 10 days while B can do the same work in 20 days. They start together but A leaves after three days. How many days will B take to complete the remaining work?

A)
14 days

B)
8 days

C)
12 days

D)
11 days


Correct Answer :

11 days


Explanation :

One day's work of A and B = (1/10 + 1/20) = 3/20

Work done by A and B together in the 3 days = 3 (1/10 + 1/20) = 9/20
Remaining Work =1- 9/20 = 11/20

1/20 Work done by B in a day
thus,11/20 Work wll be done by B in (11/20)*20 =11 days

If 3 men or 4 women can reap a field in 30 days, how long will 3 men and 6 women take to reap it?

A)
21 days

B)
16 days

C)
18 days

D)
12 days


Correct Answer :

12 days


Explanation :

3 men can complete work in 30 days
so, Work done by one man in a day = 1/(3*30)
and Work done by one women in a day =1/(4*30))

Thus, 3 men and 6 women will work in a day => 3/(3*30) + 6/(4*30)
= 1/30( 1 + 6/4)
= (1/30)*(10/4) =>1/12

3 men and 6 women do 1/12th part of work in a day,so they will complete the work in 12 days

A is twice as good a workman as B, and finishes the work in 14 days less than B. In how many days can it be done by A alone?

A)
14

B)
21

C)
28

D)
42


Correct Answer :

14


Explanation :

let A take X days to complete the work and B takes 2X days
according to question, A takes 14 days less than B, that is X = 2X – 14 =>14

thus ,A take 14 days to complete the work and B takes 28 days.

30 persons can do a piece of work in 24 days. How many more people are required to complete the work in 20 days?

A)
4

B)
5

C)
6

D)
10


Correct Answer :

6


Explanation :

let X persons required to complete the work in 20 days
then, work done => 30 * 24 = X *20

thus ,num of persons, X = 720 / 20 => 36

extra ,more people required = 36 - 30 = 6 persons

A is twice as good workman as B. Together, they finish the work in 14 days. In how many days can it be finish by B separately?

A)
21

B)
48

C)
42

D)
35


Correct Answer :

42


Explanation :

let A take X days to complete the work and B takes 2X days
(A+B) one day work = 1/X + 1/2X = 1/14
=>14+7=X
=>X=21

Thus ,
B working alone will require 2*21=42 days to complete the work
A working alone will require 21 days to complete the work

A can do a piece of work in 30 days while B can do it in 40 days. In how many days can A and B working together do it ?

A)
70 days

B)
171/4 days

C)
190/7 days

D)
120/7 days


Correct Answer :

120/7 days


Explanation :

If X can do a piece of work in n days, then X's 1 day's work =1/n

Then (A + B)'s 1 day's work = (1/30 + 1/40) = 7/120
Hence, Time taken by both to finish the work = 120/7 days

A can do a piece of work in 20 days which B can do in 12 days. B worked at it for 9 days. A can finish the remaining work in ?

A)
3 days

B)
5 days

C)
7 days

D)
11 days


Correct Answer :

5 days


Explanation :

If X can do a piece of work in n days, then X's 1 day's work =1/n

B's 9 day's work = 9 * (1/12) = 3/4
Remaining work = (1 - 3/4) = 1/4
1/4 work is done by A in = 20 * (1/4) = 5 day

A and B together can do a work in 8 days. If A alone can do it in 12 days, then in how many days can B alone do it?

A)
12 days

B)
20 days

C)
24 days

D)
28 days


Correct Answer :

24 days


Explanation :

If X can do a piece of work in n days, then X's 1 day's work =1/n
If A and B, working together,and can complete a piece of work in X days. If A, working alone, can
complete the work in Y days, then B working alone, will complete the work in XY/(Y-X) days.

Then ,B alone can complete = (12 * 8) / (12 - 8) = 96/4 = 24 days

A can do a piece of work in 12 days. B is 60% more efficient than A. The number of days, it take B to do the same piece of work is ?

A)
15/2

B)
25/4

C)
8

D)
6


Correct Answer :

15/2


Explanation :

A's 1 day's work = 1/12
B's 1 day's work = 1/12 + 60% of 1/12 = 1/12 x 160/100 = 2/15

Hence,B can do the work in 15/2 days

X is 4 times more efficient than Y, in what proportion will the number of days taken by X and Y to complete any work?

A)
8 : 1

B)
1 : 5

C)
6 : 8

D)
5 : 1


Correct Answer :

1 : 5


Explanation :

If A is twice as good a workman as B, then:
(a) Ratio of work done by A and B is 2:1.
(b) Ratio of times taken by by A and B to finish a work is 1:2.

Efficiency (X : Y) = 5 : 1
No. of days (X : Y) = 1 : 5

20 persons completed 1/3 rd of the work in 12 days. How many more person are required to finish the rest work in next 12 days?

A)
20

B)
12

C)
18

D)
40


Correct Answer :

20


Explanation :

Work done by 20 persons = 1/3
Remaining work = 1- 1/3 = 2/3
So for double work in same days we need double number of people i.e. 40.

Hence, 20 more people are needed.

6 children and 2 men complete a certain piece of work in six days. Each child takes twice the time taken by a man to finish the work. In how many days will 5 men finish the same work?

A)
6

B)
8

C)
9

D)
15


Correct Answer :

6


Explanation :

6C + 2M = 6 days
36C + 12M = 1 day
As is given 1M = 2C
Then, 36C +12*2C = 1 day
60 children can work in 1 day
Now, 5 men = 10 children
Then, 10 children can work in 6 days.So 5 men also can complete the work in 6 days.

If 6 men and 8 boys can do a piece of work in 10 days while 26 men and 48 boys can do the same work in 2 days,then the time taken by 15 men and 20 boys in doing the same type of work will be?

A)
4

B)
6

C)
8

D)
9


Correct Answer :

4


Explanation :

Let a man one day work is X and a boy one day work is Y. Then
6x + 8y =1/10
26x + 48y =1/2
After resolving above equations

x =1/100
y =1/200

15x + 20y = 15/100+20/200 = 1/4
Hence, 15 men and 20 boys to do that work in 4 days

6 men or 10 women can reap a field in 15 days, then the number of days that 12 men and 5 women will take to reap the same field is :

A)
5

B)
6

C)
8

D)
12


Correct Answer :

6


Explanation :

Work done by 6 men = work done by 10 women.
Work done by 1 man = work done by 10 / 6 women= 5/3 women

∴ 12 men + 5 women = 12 x ( 5 / 3) + 5 = 25 women
∴ W1 * D1 = W2 * D2 [W = women, D=days]
10 * 15 = 25 * D2
D2 = 6

Latest Updates

Profit and Loss

The cost price of 20 articles is equal to the selling price of 16 articles. Find the gain or loss percent?

Discount

Successive discount of 10% and 10% are equivalent to a single discount of ?

A discount series of 10%, 20% and 40% is equal to single discount of ?

Pepsi and Coke, there are two companies, selling the packs of cold­drinks. For the same selling price Pepsi gives two successive discounts of 10% and 25% on marked price, while Coke sells it by giving two successive discounts of 15% and 20% on marked price. What is the ratio of their marked price?

Percentage

If x is 15% of y and y is 40% of z, then x+y is what % of z ?

Time and Distance

While going form A to B, Rahman drove at 40 km an hour but while coming back he drove at only 24 km an hour. what was the average speed (in km/hr) at which he drove ?

Numbers

The number of natural numbers less than 100 which have exactly 3 factors is ?

Height and Distance

The difference in the length of the shadow of a 10 m high pole when the angles of elevation of the sun are 30° and 60° is

Indian History

Who among the following social reformers had founded the Ramakrishna Mission ?

Physics

Who received the first Nobel Prize in physics?

Which among the following is the SI unit of Force?

Atmospheric pressure at sea level equals ?

General Knowledge of India

Which of the following dance forms was introduced by the great Vaishnava saint and reformer Mahapurusha Sankaradeva ?

Which of the following is the only classical dance of india having links with Muslim culture and represents a unique synthesis of Hindu and Muslim genius in art ?

Time and Distance

Starting from the same point at the same time, Ruhan and Yuvan had to reach the same destination. While Ruhan drove at 45 km/hr, Yuvan was slower by 5 km/hr. If Yuvan arrived at the destination an hour after Ruhan did, the distance covered by each, in Kilometres, was ?

Simple Interest

A sum of money was invested at a certain rate of simple interest for 4 years. Had the sum been invested at a rate 3% higher than the actual rate, the interest earned would have been 720 Rs more. Find the sum initially invested?

Ratio and Proportion

A bag contains red, blue and black balls. The ratio of red to blue balls is 3 : 5. The ratio of black to red balls is 3 : 4. What is the ratio of blue to black balls?

Profit and Loss

Selling a pack of incense sticks for 136 Rs resulted in a loss of 15%. To make a profit of 10%, the selling price should be ?